Work Package 1: Requirement analysis
JULY 2012-MARCH 2013
Deliverable Start Finish Status
D1.1 Study and Registration of ontology's requirements July 2012 December 2012 Delivered
D1.2 Study and Registration of the requirements of Case Based Reasoning applications - Case studies from companies on real application conditions July 2012 March 2013 Delivered

Work Package 2: Ontology Registration
JANUARY 2013-DECEMBER 2013
Deliverable Start Finish Status
D2.1 Description of the objects and qualities of the ontology January 2013 June 2013 Delivered
D2.2 Ontology developed in XML data representation January 2013 December 2013 Delivered
D2.3 Ontology developed in OWL-DL standard January 2013 December 2013 Delivered

Work Package 3: CBR based technique development based on combinatorial algorithms
JULY 2013-DECEMBER 2014
Deliverable Start Finish Status
D3.1 Architecture of the CBR system July 2013 December 2013 Delivered
D3.2 Development of the CBR system July 2013 December 2014 70% completed
D3.3 Evaluation of the results July 2013 December 2014 30% completed

Work Package 4: Development of SWRL rules and SQWRL application for a web-based CBR application
JULY 2013-DECEMBER 2014
Deliverable Start Finish Status
D4.1 Registration and development of SWRL rules July 2013 December 2013 Delivered
D4.2 Development of CBR system based on OWL, SWRL and SQWRL July 2013 December 2014 20% completed
D4.3 Evaluation of the results July 2013 December 2014 0% completed

Work Package 5: Evaluation and dissemination of results
JULY 2012-JUNE 2015
Deliverable Start Finish Status
D5.1 Complete report on project evaluation and comparison between the combinatorial based and the semantic SQWRL CBR system July 2012 June 2015 0% completed
D5.2 Project Website July 2012 September 2012 Delivered (continuously updating website)
Timeline per year

2012

July
August
September
October
November
December
Start WP1(Deliverables D1.1,D1.2) and WP5 (Deliverables D5.1,D5.2) Working on project
Finish D5.2
Working on project Working on project
Finish D1.1

2013

January
February
March
April
May
June
Start WP2 (Deliverables D2.1,D2.2) Working on project
Finish D1.2
Working on project Working on project
Finish D2.1
July
August
September
October
November
December
Start WP3 (Deliverables D3.1,D3.2,D3.3) and WP4 (Deliverables D4.1,D4.2,D4.3) Working on project Working on project Working on project Working on project
Finish D2.2,D2.3 (Consequently finish WP2) D3.1,D4.1

2014

January
February
March
April
May
June
Working on project Working on project Working on project Working on project Working on project Working on project
July
August
September
October
November
December
Working on project Working on project Working on project Working on project Working on project
Finish D3.2, D3.3 (Consequently finish WP3),D4.2 and D4.3 (Consequently finish WP4)

2015

January February March April May June
Working on project Working on project Working on project Working on project Working on project
Finish D5.1 and finally whole project